On track
Second carriageway linking Haswa city to the expressway
Roads and bridges project No. 292 in Babil.
انشاء الممر الثاني لربط مدينة الحصوة بالمرور السريع
Actual progress 12% as of 1 Jun 2026
Where the plan says it should be 7%
Progress against plan
Contract ends 3 Aug 2027
Timeline
2025
2027
- Started
- 11 Dec 2025
- Contract end
- 3 Aug 2027
- Running for
- 0.5 years
- Data as of
- 1 Jun 2026