Past contract end
Residential complex in Diyala, Khalis
Housing project No. 73 in Diyala.
انشاء مجمع سكني في محافظة ديالى/ الخالص
Actual progress 68% as of 1 Jun 2026
Where the plan says it should be 100% 32.1 points behind
Progress against plan
Contract ended 30 May 2024, 732 days before the data date
Timeline
2019
Contract end
2026
- Started
- 7 Jul 2019
- Contract end
- 30 May 2024
- Running for
- 6.9 years
- Data as of
- 1 Jun 2026