On track

Qadisiya water project in Salah al-Din (2009)

Water project No. 213 in Salah al-Din.

مشروع ماء القادسية في محافظ صلاح الدين/2009

Actual progress 77% as of 1 Jun 2026
Where the plan says it should be 46%

Progress against plan

Contract ends 12 Jan 2028

Timeline

Started
16 Jul 2012
Contract end
12 Jan 2028
Running for
13.9 years
Data as of
1 Jun 2026