On track

21 lift stations in Diwaniyah province

Sewage project No. 153 in Al-Qadisiyah (Diwaniyah).

مشروع محطات الرفع عدد 21 محطة في محافظة الديوانية

Actual progress 16% as of 1 Jun 2026
Where the plan says it should be 16%

Progress against plan

Contract ends 22 Jul 2027

Timeline

Started
11 May 2025
Contract end
22 Jul 2027
Running for
1.1 years
Data as of
1 Jun 2026