Removal of the temporary steel bridge and construction of the Al-Ali concrete bridge

Roads and bridges project No. 327 in Basra.

ازالة الجسر الحديدي المؤقت وانشاء جسر العلي الكونكريتي

When will the Removal of the temporary steel bridge and construction of the Al-Ali concrete bridge be finished? The contract end date was 22 Mar 2026. As of 1 Jun 2026 the Ministry of Construction reported it 87.5% complete, against 100% planned. The published data gives no revised completion date.

Actual progress 87.5% as of 1 Jun 2026
Where the plan says it should be 100% 12.5 points behind

Progress against plan

Contract ended 22 Mar 2026, 71 days before the data date

Timeline

Started
5 Feb 2025
Contract end
22 Mar 2026
Running for
1.3 years
Data as of
1 Jun 2026