Behind plan

Martyr Izz al-Din Salim bridge, 312 m, Basra

Roads and bridges project No. 328 in Basra.

انشاء جسر الشهيد عز الدين سليم بطول 312 م / البصرة

When will the Martyr Izz al-Din Salim bridge, 312 m, Basra be finished? The contract end date is 6 Jun 2026. As of 1 Jun 2026 the Ministry of Construction reported it 64.5% complete, against 95% planned. The published data gives no revised completion date.

Actual progress 64.5% as of 1 Jun 2026
Where the plan says it should be 95% 30.5 points behind

Progress against plan

30.5 points below planned progress

Timeline

Started
25 Feb 2013
Contract end
6 Jun 2026
Running for
13.3 years
Data as of
1 Jun 2026