On track

Rehabilitation of the diplomatic quarter in Baghdad, Amiriya area

Buildings project No. 10 in Baghdad.

اعادة تأهيل الحي الدبلوماسي في العاصمة بغداد / منطقة العامرية

Actual progress 59% as of 1 Jun 2026
Where the plan says it should be 45.6%

Progress against plan

Contract ends 27 Apr 2027

Timeline

Started
30 Oct 2024
Contract end
27 Apr 2027
Running for
1.6 years
Data as of
1 Jun 2026