Past contract end
Link from the government complex to Expressway No. 1 at km 100
Roads and bridges project No. 334 across several provinces.
ربط المجمع الحكومي بطريق المرور السريع رقم 1 في المحطة الكم( 100)
Actual progress 94.2% as of 1 Jun 2026
Where the plan says it should be 100% 5.8 points behind
Progress against plan
Contract ended 17 Dec 2025, 166 days before the data date
Timeline
2023
2026
- Started
- 9 Apr 2023
- Contract end
- 17 Dec 2025
- Running for
- 3.1 years
- Data as of
- 1 Jun 2026