On track
Supply, construction, operation and maintenance of the treatment plant (Hamdan treatment center, phase 5)
Sewage project No. 186 in Basra.
تجهيز وتنفيذ وتشغيل وصيانة لمحطة المعالجة (مركز تصفية حمدان م5)
Actual progress 85% as of 1 Jun 2026
Where the plan says it should be 78%
Progress against plan
Contract ends 21 Dec 2026
Timeline
2020
2026
- Started
- 22 Dec 2020
- Contract end
- 21 Dec 2026
- Running for
- 5.4 years
- Data as of
- 1 Jun 2026