On track

Supply, construction, operation and maintenance of the treatment plant (Hamdan treatment center, phase 4)

Sewage project No. 185 in Basra.

تجهيز وتنفيذ وتشغيل وصيانة لمحطة المعالجة (مركز تصفية حمدان م4)

Actual progress 85.7% as of 1 Jun 2026
Where the plan says it should be 84.2%

Progress against plan

Contract ends 6 Oct 2026

Timeline

Started
21 Nov 2013
Contract end
6 Oct 2026
Running for
12.5 years
Data as of
1 Jun 2026