On track
Supply, construction, operation and maintenance of the treatment plant (Hamdan treatment center, phase 4)
Sewage project No. 185 in Basra.
تجهيز وتنفيذ وتشغيل وصيانة لمحطة المعالجة (مركز تصفية حمدان م4)
Actual progress 85.7% as of 1 Jun 2026
Where the plan says it should be 84.2%
Progress against plan
Contract ends 6 Oct 2026
Timeline
2013
2026
- Started
- 21 Nov 2013
- Contract end
- 6 Oct 2026
- Running for
- 12.5 years
- Data as of
- 1 Jun 2026