Past contract end

Supply and construction of stormwater trunk lines with a lift station, right bank of Mosul, phase 4

Sewage project No. 117 in Nineveh.

تجهيز وتنفيذ الخطوط الناقله المطرية مع محطة الرفع الجانب الايمن لمدينة الموصل م4

Actual progress 96.2% as of 1 Jun 2026
Where the plan says it should be 100% 3.8 points behind

Progress against plan

Contract ended 10 Feb 2025, 476 days before the data date

Timeline

Started
24 Feb 2014
Contract end
10 Feb 2025
Running for
12.3 years
Data as of
1 Jun 2026