Uruba (Radio) overpass, Diwaniyah
Municipal services project No. 196 in Al-Qadisiyah (Diwaniyah).
انشاء مجسر العروبة (الاذاعة) في محافظة الديوانية
When will the Uruba (Radio) overpass, Diwaniyah be finished? The contract end date was 22 Nov 2025. As of 1 Jun 2026 the Ministry of Construction reported it 15.3% complete, against 100% planned. The published data gives no revised completion date.
Actual progress 15.3% as of 1 Jun 2026
Where the plan says it should be 100% 84.8 points behind
Progress against plan
Contract ended 22 Nov 2025, 191 days before the data date
Timeline
2024
Contract end
2026
- Started
- 27 Nov 2024
- Contract end
- 22 Nov 2025
- Running for
- 1.5 years
- Data as of
- 1 Jun 2026