Past contract end

Uruba (Radio) overpass, Diwaniyah

Municipal services project No. 196 in Al-Qadisiyah (Diwaniyah).

انشاء مجسر العروبة (الاذاعة) في محافظة الديوانية

When will the Uruba (Radio) overpass, Diwaniyah be finished? The contract end date was 22 Nov 2025. As of 1 Jun 2026 the Ministry of Construction reported it 15.3% complete, against 100% planned. The published data gives no revised completion date.

Actual progress 15.3% as of 1 Jun 2026
Where the plan says it should be 100% 84.8 points behind

Progress against plan

Contract ended 22 Nov 2025, 191 days before the data date

Timeline

Started
27 Nov 2024
Contract end
22 Nov 2025
Running for
1.5 years
Data as of
1 Jun 2026