Behind plan

Textile (Naseej) overpass, Diwaniyah

Municipal services project No. 199 in Al-Qadisiyah (Diwaniyah).

انشاء مجسر النسيج في محافظة الديوانية

When will the Textile (Naseej) overpass, Diwaniyah be finished? The contract end date is 21 Nov 2026. As of 1 Jun 2026 the Ministry of Construction reported it 29.9% complete, against 78.8% planned. The published data gives no revised completion date.

Actual progress 29.9% as of 1 Jun 2026
Where the plan says it should be 78.8% 48.9 points behind

Progress against plan

48.9 points below planned progress

Timeline

Started
21 Nov 2024
Contract end
21 Nov 2026
Running for
1.5 years
Data as of
1 Jun 2026