Behind plan
Textile (Naseej) overpass, Diwaniyah
Municipal services project No. 199 in Al-Qadisiyah (Diwaniyah).
انشاء مجسر النسيج في محافظة الديوانية
When will the Textile (Naseej) overpass, Diwaniyah be finished? The contract end date is 21 Nov 2026. As of 1 Jun 2026 the Ministry of Construction reported it 29.9% complete, against 78.8% planned. The published data gives no revised completion date.
Actual progress 29.9% as of 1 Jun 2026
Where the plan says it should be 78.8% 48.9 points behind
Progress against plan
48.9 points below planned progress
Timeline
2024
2026
- Started
- 21 Nov 2024
- Contract end
- 21 Nov 2026
- Running for
- 1.5 years
- Data as of
- 1 Jun 2026