Residential complex in Maysan, Abu Rumana
Housing project No. 92 in Maysan.
انشاء مجمع سكني في محافظة ميسان/ أبو رمانة
Actual progress 92.2% as of 1 Jun 2026
Where the plan says it should be 100% 7.8 points behind
Progress against plan
Contract ended 21 Feb 2026, 100 days before the data date
Timeline
2019
2026
- Started
- 22 Sept 2019
- Contract end
- 21 Feb 2026
- Running for
- 6.7 years
- Data as of
- 1 Jun 2026