Past contract end

Residential complex in Maysan, Abu Rumana

Housing project No. 92 in Maysan.

انشاء مجمع سكني في محافظة ميسان/ أبو رمانة

Actual progress 92.2% as of 1 Jun 2026
Where the plan says it should be 100% 7.8 points behind

Progress against plan

Contract ended 21 Feb 2026, 100 days before the data date

Timeline

Started
22 Sept 2019
Contract end
21 Feb 2026
Running for
6.7 years
Data as of
1 Jun 2026