Housing projects in Maysan
The Ministry of Construction lists 6 housing projects in Maysan: 1 past contract end, 2 behind plan, 2 on track, 1 completed, as of 1 Jun 2026.
Completed1
On track2
Behind plan2
Past contract end1
Residential complex in Maysan, Abu Rumana Contract ended 21 Feb 2026, 100 days before the data date Past contract end Residential complex in Maysan, Martyrs Foundation 19.1 points below planned progress Behind plan Residential complex in Maysan, Kumait 62.7 points below planned progress Behind plan Residential complex in Maysan, Qal'at Salih No contract end date given On track Residential complex in Maysan, Majar al-Kabir No contract end date given On track Rural housing units in the marshes of Basra, Maysan and Dhi Qar (marshes revival program) Completed
Source: Ministry of Construction, status as of 1 Jun 2026Details