On track

Rehabilitation and maintenance of the remaining parts of the Daquq bridge

Roads and bridges project No. 260 in Kirkuk.

تأهيل وصيانة الاجزاء المتبقية من جسر داقوق

When will the Rehabilitation and maintenance of the remaining parts of the Daquq bridge be finished? The contract end date is 20 Jul 2026. As of 1 Jun 2026 the Ministry of Construction reported it 53% complete, against 49.1% planned. The published data gives no revised completion date.

Actual progress 53% as of 1 Jun 2026
Where the plan says it should be 49.1%

Progress against plan

Contract ends 20 Jul 2026

Timeline

Started
1 Jan 2026
Contract end
20 Jul 2026
Running for
0.4 years
Data as of
1 Jun 2026