On track
Rehabilitation and maintenance of the remaining parts of the Daquq bridge
Roads and bridges project No. 260 in Kirkuk.
تأهيل وصيانة الاجزاء المتبقية من جسر داقوق
When will the Rehabilitation and maintenance of the remaining parts of the Daquq bridge be finished? The contract end date is 20 Jul 2026. As of 1 Jun 2026 the Ministry of Construction reported it 53% complete, against 49.1% planned. The published data gives no revised completion date.
Actual progress 53% as of 1 Jun 2026
Where the plan says it should be 49.1%
Progress against plan
Contract ends 20 Jul 2026
Timeline
2026
2026
- Started
- 1 Jan 2026
- Contract end
- 20 Jul 2026
- Running for
- 0.4 years
- Data as of
- 1 Jun 2026