Past contract end

Rehabilitation of the Baghdad to Abu Ghraib expressway

Roads and bridges project No. 331 across several provinces.

مشروع تأهيل طريق المرور السريع (بغداد-ابو غريب)

Actual progress 76% as of 1 Jun 2026
Where the plan says it should be 100% 24 points behind

Progress against plan

Contract ended 7 Dec 2025, 176 days before the data date

Timeline

Started
18 Jan 2025
Contract end
7 Dec 2025
Running for
1.4 years
Data as of
1 Jun 2026