Past contract end

Rehabilitation of 12 residential neighbourhoods in Diwaniyah

Sewage project No. 152 in Al-Qadisiyah (Diwaniyah).

مشروع تأهيل الأحياء السكنية (12 حي) في الديوانية

Actual progress 66.3% as of 1 Jun 2026
Where the plan says it should be 100% 33.7 points behind

Progress against plan

Contract ended 21 May 2026, 11 days before the data date

Timeline

Started
4 Mar 2025
Contract end
21 May 2026
Running for
1.2 years
Data as of
1 Jun 2026