Past contract end
Rehabilitation of 12 residential neighbourhoods in Diwaniyah
Sewage project No. 152 in Al-Qadisiyah (Diwaniyah).
مشروع تأهيل الأحياء السكنية (12 حي) في الديوانية
Actual progress 66.3% as of 1 Jun 2026
Where the plan says it should be 100% 33.7 points behind
Progress against plan
Contract ended 21 May 2026, 11 days before the data date
Timeline
2025
2026
- Started
- 4 Mar 2025
- Contract end
- 21 May 2026
- Running for
- 1.2 years
- Data as of
- 1 Jun 2026