Past contract end
Zurbatiyah border crossing, remaining works on the passenger building
Buildings project No. 19 in Wasit.
منفذ زرباطية الحدودي/تنفيذ المتبقي من أعمال مبنى المسافرين
Actual progress 18% as of 1 Jun 2026
Where the plan says it should be 68% 50 points behind
Progress against plan
Contract ended 10 Apr 2026, 52 days before the data date
Timeline
2025
Contract end
2026
- Started
- 20 Oct 2025
- Contract end
- 10 Apr 2026
- Running for
- 0.6 years
- Data as of
- 1 Jun 2026