On track
Diwaniyah to Hilla main road, phase one, 25.3 km
Roads and bridges project No. 312 in Al-Qadisiyah (Diwaniyah).
مشروع ديوانية -حلة الرئيسي المرحلة الاولى بطول 25.3 كم في محافظة الديوانية
Actual progress 62.3% as of 1 Jun 2026
Where the plan says it should be 55.1%
Progress against plan
Contract ends 10 Jun 2026
Timeline
2025
2026
- Started
- 28 Jan 2025
- Contract end
- 10 Jun 2026
- Running for
- 1.3 years
- Data as of
- 1 Jun 2026