Past contract end

Shafiya water project in Diwaniyah (2024)

Water project No. 240 in Al-Qadisiyah (Diwaniyah).

مشروع ماء الشافعية / محافظة الديوانية /2024

Actual progress 98.1% as of 1 Jun 2026
Where the plan says it should be 98%

Progress against plan

Contract ended 24 Jan 2026, 128 days before the data date

Timeline

Started
2 Jul 2024
Contract end
24 Jan 2026
Running for
1.9 years
Data as of
1 Jun 2026