Drinking water projects in Al-Qadisiyah (Diwaniyah)
The Ministry of Construction lists 6 drinking water projects in Al-Qadisiyah (Diwaniyah): 2 past contract end, 1 behind plan, 3 on track, as of 1 Jun 2026.
On track3
Behind plan1
Past contract end2
Shamiya water project in Diwaniyah (2010) Contract ended 31 Jul 2025, 305 days before the data date Past contract end Shafiya water project in Diwaniyah (2024) Contract ended 24 Jan 2026, 128 days before the data date Past contract end National water and sanitation master plan for the cities, districts and subdistricts of Diwaniyah 34.2 points below planned progress Behind plan Water trunk lines in Diwaniyah Contract ends 26 Jan 2027 On track Daghara and Sumer water project in Diwaniyah Contract ends 8 Feb 2027 On track Mahnawiya water project, capacity 1,000 m3 per hour Contract ends 14 Dec 2026 On track
Source: Ministry of Construction, status as of 1 Jun 2026Details