On track

Completion of study, design and construction of Siniya sewage (turnkey) with infrastructure development for Siniya subdistrict

Sewage project No. 126 in Salah al-Din.

إكمال دراسة وتصاميم وتنفيذ مجاري الصينية/تسليم مفتاح مع تطوير البنى التحتية الخاصة بناحية الصينية

Actual progress 39.5% as of 1 Jun 2026
Where the plan says it should be 37.2%

Progress against plan

Contract ends 23 Aug 2028

Timeline

Started
8 Nov 2023
Contract end
23 Aug 2028
Running for
2.6 years
Data as of
1 Jun 2026