Past contract end
Supply, construction, operation and maintenance of the treatment plant, sewage and stormwater networks, lift stations, trunk lines and outfalls for Samarra, phase 2
Sewage project No. 122 in Salah al-Din.
تجهيز وتنفيذ وتشغيل وصيانة محطة المعالجة وشبكات المجاري الثقيلة والمطرية ومحطات الرفع والخطوط الناقلة مع المذبات لمدينة سامراء / م 2
Actual progress 88% as of 1 Jun 2026
Where the plan says it should be 100% 12 points behind
Progress against plan
Contract ended 27 Dec 2024, 521 days before the data date
Timeline
2020
Contract end
2026
- Started
- 25 Feb 2020
- Contract end
- 27 Dec 2024
- Running for
- 6.3 years
- Data as of
- 1 Jun 2026