Past contract end

Expressway section T/6, right lane, km 0 to km 47

Roads and bridges project No. 332 across several provinces.

مشروع المرور السريع ط/6 الممر الايمن المقطع كم ـ(000+0) - ـ(000+47)

Actual progress 85.2% as of 1 Jun 2026
Where the plan says it should be 100% 14.8 points behind

Progress against plan

Contract ended 20 May 2025, 377 days before the data date

Timeline

Started
10 Nov 2011
Contract end
20 May 2025
Running for
14.6 years
Data as of
1 Jun 2026