Past contract end
Expressway section T/6, right lane, km 0 to km 47
Roads and bridges project No. 332 across several provinces.
مشروع المرور السريع ط/6 الممر الايمن المقطع كم ـ(000+0) - ـ(000+47)
Actual progress 85.2% as of 1 Jun 2026
Where the plan says it should be 100% 14.8 points behind
Progress against plan
Contract ended 20 May 2025, 377 days before the data date
Timeline
2011
2026
- Started
- 10 Nov 2011
- Contract end
- 20 May 2025
- Running for
- 14.6 years
- Data as of
- 1 Jun 2026