Completed
Muthanna construction laboratory
Buildings project No. 62 in Muthanna.
أنشاء مختبر المثنى الأنشائي
Actual progress 100% as of 1 Jun 2026
Where the plan says it should be 100%
Progress against plan
Timeline
2022
Contract end
2026
- Started
- 24 Jan 2022
- Contract end
- 14 May 2024
- Running for
- 4.4 years
- Data as of
- 1 Jun 2026