On track

Remaining works on neighbourhood networks, phases 2 and 3, Diwaniyah

Sewage project No. 156 in Al-Qadisiyah (Diwaniyah).

الاعمال المتبقية من شبكات احياء المرحلة 2, 3 / محافظة الديوانية

Actual progress 45% as of 1 Jun 2026
Where the plan says it should be 40%

Progress against plan

Contract ends 31 Jan 2027

Timeline

Started
28 Jul 2025
Contract end
31 Jan 2027
Running for
0.8 years
Data as of
1 Jun 2026