Past contract end

Second carriageway of the Butaira, Fajr and Al Budair road, 52.35 km

Roads and bridges project No. 329 across several provinces.

انشاء الممر الثاني لطريق بتيرة -الفجر -ال بدير بطول 52.35كم

Actual progress 88.8% as of 1 Jun 2026
Where the plan says it should be 100% 11.2 points behind

Progress against plan

Contract ended 1 Nov 2025, 212 days before the data date

Timeline

Started
13 Jan 2022
Contract end
1 Nov 2025
Running for
4.4 years
Data as of
1 Jun 2026