Project tracker
All 389 Ministry of Construction projects, with planned and actual progress, as of 1 Jun 2026.
completed100
on track98
behind plan49
past contract end112
Rehabilitation of the Sabian Mandaean mandi (temple) in Kirkuk No contract end date given On track Rehabilitation of Jalawla General Hospital Contract ended 18 Apr 2026, 44 days before the data date Past contract end Construction of the National Human Rights Network office building in Anbar Contract ended 25 Dec 2025, 158 days before the data date Past contract end Construction laboratory building in Anbar Contract ended 26 Dec 2025, 157 days before the data date Past contract end Supply of imported laboratory equipment for testing construction materials for the National Center for Construction Laboratories in Baghdad and the provinces No contract end date given On track Rehabilitation of the minaret of the Khulafa Mosque Contract ends 15 Jul 2027 On track Additional floor for the Engineering Reconstruction Directorate building Contract ended 1 May 2026, 31 days before the data date Past contract end Reconstruction of the Ministry of Planning building complex (C, D, E, F, H, I, J, K, L) 10.7 points below planned progress Behind plan Iraqi building codes and application of Arab codes No contract end date given On track Rehabilitation of the diplomatic quarter in Baghdad, Amiriya area Contract ends 27 Apr 2027 On track Completion works for the Grand Festivities Square and Unknown Soldier Monument, Baghdad Contract ends 7 Dec 2026 On track Unified bill of quantities (standard price analysis guide) No contract end date given On track Studies, designs and design review for an annex building for the Building Research Directorate No contract end date given On track Expansion of the National Center for Engineering Consultancy building No contract end date given On track Rehabilitation of the Sabian Mandaean cemetery in Baghdad, Abu Ghraib No contract end date given On track Studies, designs and design review for the Karbala traffic directorate building No contract end date given On track Phase three of the shrine of Martyr Mohammed Baqir al-Sadr 10.3 points below planned progress Behind plan Power supply for the Zurbatiyah border crossing project No contract end date given On track Zurbatiyah border crossing, remaining works on the passenger building Contract ended 10 Apr 2026, 52 days before the data date Past contract end Engineering consultancy contract to review the designs of the commercial section No contract end date given On track Zurbatiyah border crossing, commercial section Contract ended 17 May 2026, 15 days before the data date Past contract end Rehabilitation of Sabian Mandaean cemeteries in Dhi Qar No contract end date given On track Construction of the residential complex in Basra No contract end date given On track Cancer treatment and bone marrow transplant center, Duhok Completed Consultation clinic in Shorish subdistrict, Sulaymaniyah Completed Emergency hospital in Ranya, Sulaymaniyah Completed Urban statistics section building, Nineveh Completed Ministry of Planning building complex in Nineveh Completed Rehabilitation of Mar Mattai Monastery and construction of the theological institute in Bashiqa Completed National Human Rights Network office in Nineveh Completed Reconstruction and rehabilitation of the Ministry of Construction offices in Nineveh Completed Rest house for Ministry of Construction staff in Kirkuk Completed Rest house for Ministry of Construction staff in Salah al-Din Completed Statistics building for Balad district Completed National Human Rights Network office in Salah al-Din Completed Studies, designs, reconstruction and rehabilitation of the shrine of Sayyid Muhammad bin Ali al-Hadi in Salah al-Din Completed Studies and designs for the visitors' city at the shrine of Sayyid Muhammad bin Ali al-Hadi in Balad, Salah al-Din Completed State Real Estate Directorate office buildings in Anbar Completed Rest house for Ministry of Construction staff in Anbar Completed Fallujah statistics section headquarters Completed Rehabilitation of the Grand Festivities Square Completed Chaldean Patriarchate of Babylon building and fittings Completed Building for the Expressways Directorate Completed Building for the General Authority for Buildings Completed Building for the Baghdad Roads and Bridges Directorate Completed National Human Rights Network office in Babil Completed Studies, designs, reconstruction and rehabilitation of the shrine of Sharifa bint al-Hasan in Babil Completed State Real Estate Directorate office buildings in Karbala Completed Rest house for Ministry of Construction staff in Karbala Completed Studies, designs, rehabilitation and reconstruction of the shrine of Awn bin Abdullah in Karbala Completed Studies, designs and design review for a building for the Directorate for Protection of the Two Holy Shrines in Karbala Completed Ministry of Construction offices in Karbala Completed Payments for completed works, dollar exchange rate inflation amounts and unpaid deposits from the Ministry of Interior Completed State Real Estate Directorate office buildings in Wasit Completed Central Organization for Standardization and Quality Control building in Wasit Completed State Real Estate Directorate office buildings in Diwaniyah Completed Rest house for Ministry of Construction staff in Maysan Completed Rural housing units in the marshes of Basra, Maysan and Dhi Qar (marshes revival program) Completed State Real Estate Directorate office buildings in Dhi Qar Completed State Real Estate Directorate office buildings in Muthanna Completed Rest house for Ministry of Construction staff in Muthanna Completed Muthanna construction laboratory Completed Central Organization for Standardization and Quality Control building, Basra branch Completed Consultancy contract Completed Settlement of accounts for completed and cancelled projects of the Ministry of Construction Buildings Directorate Completed Soil investigations (National Human Rights Network office) Completed Residential complex in Nineveh, Tal Afar Contract ended 3 Apr 2026, 59 days before the data date Past contract end Residential complex in Nineveh, Makhmur 71 points below planned progress Behind plan Residential complex in Nineveh, Arbajiya 17.5 points below planned progress Behind plan Residential complex in Nineveh, Sinjar No contract end date given On track Residential complex in Salah al-Din, Mutarada 28.7 points below planned progress Behind plan Residential complex in Salah al-Din, Armushiya 36 points below planned progress Behind plan Residential complex in Diyala, Khalis Contract ended 30 May 2024, 732 days before the data date Past contract end Residential complex in Diyala, Ghalibiya Contract ended 8 Jul 2024, 693 days before the data date Past contract end Residential complex in Diyala, Katoun 47.2 points below planned progress Behind plan Residential complex in Anbar, Hit Contract ends 24 Nov 2027 On track Residential complex in Anbar, Jubail and Kharab Contract ends 16 Sept 2027 On track Residential complex in Anbar, Amiriyat al-Fallujah No progress data Residential complex in Baghdad, Nahrawan No contract end date given On track Residential complex in Babil, Qasim 89.2 points below planned progress Behind plan Residential complex in Karbala, Jazeera 2 Contract ended 14 May 2024, 748 days before the data date Past contract end Residential complex in Karbala, Jazeera 1 80.7 points below planned progress Behind plan Residential complex in Wasit, Aziziya Contract ended 4 Sept 2025, 270 days before the data date Past contract end Residential complex in Wasit, Suwaira Contract ends 5 Jun 2026 On track Residential complex in Wasit, Zurbatiyah Contract ends 1 Jun 2026 On track Residential complex in Diwaniyah, Housing Department homes Contract ended 3 Nov 2021, 1,671 days before the data date Past contract end Residential complex in Diwaniyah, Afak 18 points below planned progress Behind plan Residential complex in Diwaniyah, Jibsa and Shamiya Contract ended 11 Jul 2025, 325 days before the data date Past contract end Residential complex in Diwaniyah, Daghara No contract end date given On track Residential complex in Diwaniyah, Shanafiya 11.8 points below planned progress Behind plan Residential complex in Diwaniyah, Hamza al-Sharqi 14.2 points below planned progress Behind plan Residential complex in Maysan, Abu Rumana Contract ended 21 Feb 2026, 100 days before the data date Past contract end Residential complex in Maysan, Qal'at Salih No contract end date given On track Residential complex in Maysan, Martyrs Foundation 19.1 points below planned progress Behind plan Residential complex in Maysan, Majar al-Kabir No contract end date given On track Residential complex in Maysan, Kumait 62.7 points below planned progress Behind plan Residential complex in Dhi Qar, Shatra No contract end date given On track Residential complex in Dhi Qar, Qal'at Sukkar No contract end date given On track Residential complex in Dhi Qar, Suq al-Shuyukh 67.6 points below planned progress Behind plan Residential complex in Dhi Qar, Akaika 27.8 points below planned progress Behind plan Residential complex in Dhi Qar, Kashmara 1 Contract ended 9 Jan 2024, 874 days before the data date Past contract end Residential complex in Muthanna, Rumaitha 52.1 points below planned progress Behind plan Residential complex in Muthanna, Jarbouiya 67.7 points below planned progress Behind plan Residential complex in Basra, Shatt al-Arab 1 Contract ended 20 Dec 2021, 1,624 days before the data date Past contract end Residential complex in Basra, Zubair 31.3 points below planned progress Behind plan Residential complex in Basra, Shatt al-Arab 3 16.1 points below planned progress Behind plan Residential complex in Basra, Shatt al-Arab 2 48.2 points below planned progress Behind plan Residential complex in Basra, Qibla No contract end date given On track Hamdaniya sewage project, Nineveh, with phase two of the networks, treatment plant and infrastructure works Contract ends 25 Aug 2026 On track Design review, supply, construction, operation and maintenance of the Bartella sewage network and plant, Nineveh (design capacity 4,942 m3 per day) Contract ended 3 Jan 2026, 149 days before the data date Past contract end Supply and construction of the treatment plant for the left bank of Mosul (phase one) Contract ends 8 Jun 2026 On track Supply and construction of stormwater trunk lines with lift stations SL46 and SL47, left bank of Mosul Contract ended 9 Jan 2026, 143 days before the data date Past contract end Supply and construction of sewage trunk lines with four lift stations, left bank of Mosul, phase four Contract ended 3 Feb 2025, 483 days before the data date Past contract end Supply and construction of the treatment plant for the right bank of Mosul, phase 1 Contract ended 14 Jul 2024, 687 days before the data date Past contract end Supply and construction of the treatment plant for the right bank of Mosul, phase 2 Contract ends 12 Jan 2027 On track Supply and construction of the treatment plant for the left bank of Mosul (phase two) Contract ended 14 Apr 2024, 778 days before the data date Past contract end Supply and construction of stormwater trunk lines with a lift station, right bank of Mosul, phase 4 Contract ended 10 Feb 2025, 476 days before the data date Past contract end Sewage networks project, right bank of Mosul Contract ends 5 Nov 2026 On track Study and design of a treatment plant with main and branch stormwater and sewage networks and lift stations for central Kirkuk, with supply, construction, operation and maintenance of phase one (turnkey) Contract ends 28 Aug 2027 On track Hawija district sewage project, Kirkuk (infrastructure) Contract ends 17 May 2028 On track Altun Kupri district sewage, Kirkuk (infrastructure) Contract ends 18 Sept 2028 On track Supply, construction, operation and maintenance of the treatment plant, sewage and stormwater networks, lift stations, trunk lines and outfalls for Samarra, phase 2 Contract ended 27 Dec 2024, 521 days before the data date Past contract end Supply, construction, operation and maintenance of completion works for stormwater and sewage networks with lift stations for unserved neighbourhoods of Dujail Contract ends 11 Jul 2027 On track Completion works for the Balad treatment plant, phase 2, Salah al-Din, with supply, construction, operation and maintenance of phase 2 of the plant 15.1 points below planned progress Behind plan Completion works for the Tikrit (Dhuba'i) treatment plant, phase 2 Contract ended 7 Nov 2025, 206 days before the data date Past contract end Completion of study, design and construction of Siniya sewage (turnkey) with infrastructure development for Siniya subdistrict Contract ends 23 Aug 2028 On track Stormwater and sewage networks and stations for Dayoum, Tikrit district, with infrastructure development for Tikrit and Dour districts Contract ends 9 Jun 2028 On track Phase two of the Baiji sewage project, Salah al-Din (infrastructure) No progress data Supply, construction, operation and maintenance of completion works for the stormwater and sewage networks, lift stations and treatment plant of Khalis 12.7 points below planned progress Behind plan Supply, construction, operation and maintenance of completion works for stormwater and sewage networks with lift stations and treatment plant for Baquba, phase 2, Diyala Contract ended 27 Feb 2026, 94 days before the data date Past contract end Fallujah sewage project, capacity 35,000 m3 per day (turnkey) Contract ended 18 Apr 2026, 44 days before the data date Past contract end Integrated sanitation with a treatment unit for the city of Hit in Anbar Contract ends 12 Dec 2026 On track Stormwater and sewage networks for Zones 14 and 15 in Ramadi, part of the Ramadi sewage project, phase 1, Anbar Contract ended 13 Jul 2024, 688 days before the data date Past contract end Supply and construction of the stormwater drainage trunk line for the southern area, Fallujah Contract ended 22 Mar 2026, 71 days before the data date Past contract end Sewage and stormwater networks for Ana subdistrict, Anbar (infrastructure) Contract ends 8 Jun 2028 On track Sewage and stormwater networks for Kubaisa subdistrict, Anbar (infrastructure) No progress data Stormwater and sewage networks, trunk lines, lift stations and treatment plant for Kifl subdistrict, Babil (infrastructure) No progress data Stormwater networks and trunk lines to the lift station for Qasim, Hashimiya and Madhatiya, Babil (infrastructure) Contract ends 15 Nov 2029 On track Supply and construction of sewage networks for residential neighbourhoods, Karbala, phase 4 Contract ended 13 Jul 2024, 688 days before the data date Past contract end Najaf sewage treatment plant, phase 3 (design and build), Najaf No progress data Haidariya city sewage project, Najaf (infrastructure) No progress data Al-Nidaa neighbourhood sewage project, Najaf (infrastructure) Contract ends 25 Jun 2028 On track Completion of remaining works on the Aziziya sewage network, Wasit Contract ended 11 Nov 2025, 202 days before the data date Past contract end Infrastructure rehabilitation and development, phase two, Hay district Contract ends 27 Feb 2027 On track Al-Bashaer sewage project, Wasit (infrastructure) Contract ends 26 Apr 2027 On track Diwaniyah sewage project, phase 2, capacity 100,000 m3 per day (turnkey), with Noor Al-Ufuq added as main partner Contract ended 14 Jan 2026, 138 days before the data date Past contract end Ghammas sewage project, phase 1 32 points below planned progress Behind plan Study, design, construction, supply, operation and maintenance of stormwater and sewage networks with lift stations and treatment plant for Sunniya district, Diwaniyah Contract ended 31 Mar 2026, 62 days before the data date Past contract end Study, design, construction, supply, operation and maintenance of stormwater and sewage networks with lift stations and treatment plant for Mahnawiya district, Diwaniyah 29 points below planned progress Behind plan Afak sewage project Contract ends 24 Dec 2028 On track Study, design, construction, supply, operation and maintenance of stormwater and sewage networks with lift stations and treatment plant for Sumer district Contract ends 23 Oct 2026 On track Rehabilitation of 12 residential neighbourhoods in Diwaniyah Contract ended 21 May 2026, 11 days before the data date Past contract end 21 lift stations in Diwaniyah province Contract ends 22 Jul 2027 On track Study, design, construction, supply, operation and maintenance of the Ayman al-Shamiya treatment plant, right bank, Diwaniyah Contract ends 26 Jan 2027 On track Study, design, construction, supply, operation and maintenance of the Al Budair treatment plant, capacity 10,000 m3 per day, Diwaniyah 10.9 points below planned progress Behind plan Remaining works on neighbourhood networks, phases 2 and 3, Diwaniyah Contract ends 31 Jan 2027 On track Street rehabilitation in the Mechanic, Nahda 1 and Wafaa neighbourhoods No progress data Street rehabilitation in Hakim 3 neighbourhood No progress data Street rehabilitation in the Istiqama and Jamiya neighbourhoods No progress data Street rehabilitation in the Uruba 3, Muallimin and Shuhada neighbourhoods No progress data Street rehabilitation in the Sob al-Shamiya and Zahraa (behind the center) neighbourhoods No progress data Street rehabilitation in the Dubbat 1, Dubbat 2 and Adhariya neighbourhoods No progress data Street rehabilitation in the Turath and Thaqafi neighbourhoods No progress data Street rehabilitation in the Sinai and Shalabiya neighbourhoods No progress data Street rehabilitation in the Ziraiyin, Ramadan and Tamim neighbourhoods No progress data Street rehabilitation in Hakim 1 neighbourhood No progress data Street rehabilitation in the Abrar, Ansar and Adala neighbourhoods No progress data Street rehabilitation in the Uruba 1 and Uruba 2 neighbourhoods No progress data Street rehabilitation in Jazair neighbourhood No progress data Sewage and stormwater networks and trunk lines to the treatment plant of Shafiya district, Diwaniyah Contract ends 12 Aug 2027 On track Sewage and stormwater networks and trunk lines to the treatment plant of Nuffar district, Diwaniyah Contract ends 18 Sept 2027 On track Street rehabilitation in the Taqiya 1, 2 and 3 neighbourhoods No progress data Street rehabilitation in the Akrad neighbourhoods (Shahid al-Mihrab and Hakim 2) No progress data Sewage and stormwater networks and trunk lines to the treatment plant of Salahiya district, Diwaniyah Contract ends 22 Jul 2027 On track Sewage and stormwater networks, trunk lines, lift stations, force mains and the Sudair treatment plant, Diwaniyah No progress data Design and construction of sewage for Uzair and Ali al-Gharbi districts with an intermediate lift station linking the trunk line to the treatment plant, Maysan (infrastructure, design and build) No progress data Supply and construction of two Nasiriyah treatment plants (Sob al-Jazira, design capacity 70,000 m3 per day, and Sob al-Shamiya, 65,000 m3 per day) 17.3 points below planned progress Behind plan Study and design of the Shatra sewage project (treatment plant with stormwater and sewage networks and lift stations) with supply, construction and maintenance of phase one (turnkey) Contract ends 6 Feb 2028 On track Infrastructure for Suq al-Shuyukh district, Dhi Qar Contract ends 30 Jul 2029 On track Design update and construction of a treatment plant for Warka district, capacity 12,500 m3 per day, Muthanna (infrastructure) No progress data Design and construction of an integrated sewage project in Khidr district: treatment plant of 25,000 m3 per day with stormwater and sewage networks and stations, plus roads, lighting and water networks, Muthanna (infrastructure) No progress data Design update and construction of a treatment plant for Hilal and Majd districts, capacity 20,000 m3 per day, plus a sewage treatment plant for Ghadir residential city (design and build), Muthanna No progress data Design update and construction of a treatment plant for Najmi district, capacity 12,500 m3 per day, Muthanna (infrastructure) No progress data Design update and review, supply and construction of stormwater and sewage networks and stations for Samawah (small bank), with a treatment plant of 50,000 m3 per day, Muthanna (infrastructure) No progress data Supply, construction, operation and maintenance of the treatment plant (Hamdan treatment center, phase 4) Contract ends 6 Oct 2026 On track Supply, construction, operation and maintenance of the treatment plant (Hamdan treatment center, phase 5) Contract ends 21 Dec 2026 On track Supply, construction and installation of the Najaf sewage treatment plant, phase 2, design capacity 100,000 m3 per day Completed Infrastructure development and rehabilitation for Hay district Completed Infrastructure development and rehabilitation for Suwaira district Completed Completion works for the Rifai treatment plant, design capacity 60,000 m3 per day (carried out at the expense of the defaulting company Al-Barih) Completed Mosul to Sinjar ring road within Tal Afar municipality, 8,050 m, Nineveh 24.8 points below planned progress Behind plan Completion works for the Kirkuk building Contract ended 2 Feb 2026, 119 days before the data date Past contract end Approaches to the Dalla overpass, Salah al-Din 35.7 points below planned progress Behind plan Rehabilitation of the main road from Jalawla bridge to the Halwan intersection, Jalawla, Diyala Contract ended 27 Feb 2026, 94 days before the data date Past contract end Model sanitary landfill in Ramadi Contract ended 5 Nov 2025, 208 days before the data date Past contract end Uruba (Radio) overpass, Diwaniyah Contract ended 22 Nov 2025, 191 days before the data date Past contract end Jumhuriya intersection overpass, Diwaniyah Contract ended 31 May 2024, 731 days before the data date Past contract end Rehabilitation of the Daghara ring road, Diwaniyah Contract ended 26 Aug 2025, 279 days before the data date Past contract end Textile (Naseej) overpass, Diwaniyah 48.9 points below planned progress Behind plan Overpass intersections in Maysan, Butaira Contract ended 2 Sept 2025, 272 days before the data date Past contract end Completion works for street paving and development of the Zahraa and Batool residential neighbourhoods, Ali al-Gharbi district Contract ended 15 May 2025, 382 days before the data date Past contract end Overpass intersections in Maysan, Karama Contract ended 2 Mar 2025, 456 days before the data date Past contract end Overpass intersection in Dhi Qar, Iskan intersection Contract ended 23 Jun 2024, 708 days before the data date Past contract end Overpass intersection in Muthanna, Quds intersection Contract ended 13 Oct 2024, 596 days before the data date Past contract end Roads in the industrial area of Halabja Completed Concrete paving, second section of Briko quarter, Sayid Sadiq district Completed Qayyarah, Shura and Tal Abta water project, Nineveh (2010) Contract ended 18 Mar 2025, 440 days before the data date Past contract end Alqosh water project in Nineveh (2009) Contract ends 24 Apr 2027 On track National water and sanitation master plan for the cities, districts and subdistricts of Kirkuk 23 points below planned progress Behind plan Taza water project in Kirkuk (2011) Contract ended 28 Jun 2025, 338 days before the data date Past contract end Balad water project in Salah al-Din (2009) Contract ends 13 Nov 2027 On track Baiji Siniya water project, capacity 5,000 m3 per hour, and rehabilitation of the unified Baiji water project, 3,000 m3 per hour Contract ends 2 Jun 2027 On track Qadisiya water project in Salah al-Din (2009) Contract ends 12 Jan 2028 On track Khan Bani Saad water project in Diyala (2004) 43.6 points below planned progress Behind plan West Baquba water project, capacity 6,000 m3 per hour Contract ends 7 Jan 2028 On track Qara Tapa water project, capacity 2,000 m3 per hour Contract ends 13 Jul 2028 On track Jalawla water project, capacity 2,000 m3 per hour Contract ends 25 Jun 2028 On track Al-Salam and Al-Sarajiq water project in Mansuriya Contract ended 11 Apr 2023, 1,147 days before the data date Past contract end Jadidat al-Shatt water project in Diyala (2012) Contract ended 24 Mar 2026, 69 days before the data date Past contract end East Husaiba water project in Anbar (2024) Contract ends 11 Sept 2027 On track Baghdadi water project in Anbar (2008) Contract ended 3 Apr 2024, 789 days before the data date Past contract end Fallujah water project in Anbar (2004) Contract ends 2 Aug 2026 On track Kartan water project, capacity 1,000 m3 per hour 33.5 points below planned progress Behind plan Ramadi water project, capacity 10,000 m3 per hour Contract ends 2 Dec 2028 On track Zuhur subdistrict water project in Baghdad (2010) Contract ended 2 Sept 2025, 272 days before the data date Past contract end Nahrawan water project in Baghdad (2008) Contract ended 11 May 2024, 751 days before the data date Past contract end Kifl water project in Babil (2012) Contract ends 3 Apr 2027 On track Unified Hashimiya and Madhatiya water project Contract ended 25 Jul 2020, 2,137 days before the data date Past contract end Musayyib, Iskandariya and Jurf al-Sakhar water project in Babil (2009) Contract ends 19 Jun 2026 On track National water and sanitation master plan for the cities, districts and subdistricts of Karbala Contract ended 12 Feb 2026, 109 days before the data date Past contract end Khairat and western Jadwal water project in Karbala (2010) Contract ends 15 May 2027 On track South Karbala water project Contract ends 3 Sept 2029 On track National water and sanitation master plan for the cities, districts and subdistricts of Najaf 19.6 points below planned progress Behind plan Unified Najaf and Kufa water project (2008) 14.8 points below planned progress Behind plan National water and sanitation master plan for the cities, districts and subdistricts of Wasit 23.3 points below planned progress Behind plan Zubaidiya water project in Wasit (2007) Contract ended 15 Dec 2025, 168 days before the data date Past contract end Water trunk lines in Diwaniyah Contract ends 26 Jan 2027 On track National water and sanitation master plan for the cities, districts and subdistricts of Diwaniyah 34.2 points below planned progress Behind plan Daghara and Sumer water project in Diwaniyah Contract ends 8 Feb 2027 On track Shafiya water project in Diwaniyah (2024) Contract ended 24 Jan 2026, 128 days before the data date Past contract end Shamiya water project in Diwaniyah (2010) Contract ended 31 Jul 2025, 305 days before the data date Past contract end Mahnawiya water project, capacity 1,000 m3 per hour Contract ends 14 Dec 2026 On track Maimuna water project, capacity 2,000 m3 per hour Contract ends 10 Mar 2028 On track Amarah water project in Maysan (2004) Contract ended 31 Mar 2025, 427 days before the data date Past contract end National water and sanitation master plan for the cities, districts and subdistricts of Maysan Contract ends 26 Oct 2026 On track National water and sanitation master plan for the cities, districts and subdistricts of Dhi Qar Contract ended 13 May 2026, 19 days before the data date Past contract end Nasiriyah water project in Dhi Qar (2012) No contract end date given On track Samawah water project Contract ended 16 Mar 2025, 442 days before the data date Past contract end National water and sanitation master plan for the cities, districts and subdistricts of Muthanna 11.6 points below planned progress Behind plan Greater Basra water project, phase one Contract ends 27 Feb 2027 On track Greater Basra water project, phase two No contract end date given On track Study on desalination of drainage and sewage water Contract ends 20 Jul 2026 On track Dujail water project, capacity 4,000 m3 per hour Completed Kut water project, capacity 10,000 m3 per hour Completed Review of studies for the Samarra, Baladruz and Zanbour projects Completed Second carriageway of the Mosul to Kirkuk road, 124.43 km, in Kirkuk and Nineveh Contract ends 24 Apr 2027 On track Ring road with the Seventh Bridge Contract ends 21 Dec 2030 On track Rehabilitation of the Sinjar to Umm Jurais road, 35 km long and 7.4 m wide Contract ended 22 Jan 2026, 130 days before the data date Past contract end New Kuwair bridge, second carriageway next to the old Kuwair bridge Contract ends 21 Jun 2028 On track Rehabilitation and maintenance of the remaining parts of the Daquq bridge Contract ends 20 Jul 2026 On track Maintenance of the Kirkuk to Sulaymaniyah road Contract ended 23 Mar 2026, 70 days before the data date Past contract end Rehabilitation and maintenance of the Baghdad to Kirkuk road, 162 km Contract ended 2 Nov 2024, 576 days before the data date Past contract end Maintenance of the Baiji to Shirqat junction road Contract ended 22 Nov 2025, 191 days before the data date Past contract end Tikrit concrete bridge (north Tikrit bridge), approaches, phase two Contract ended 10 Feb 2026, 111 days before the data date Past contract end Balad intersection overpasses on the Baghdad to Mosul road Contract ends 30 Jun 2026 On track Zghaiton and Al-Shai bridges on the alternative Tikrit to Tuz road Contract ended 23 Aug 2021, 1,743 days before the data date Past contract end Hamrin lake concrete bridge and rehabilitation of the Muqdadiya to Saadiya main road (Hamrin lake basin) Contract ended 19 May 2026, 13 days before the data date Past contract end Rehabilitation and maintenance of the Baghdad to Kirkuk road, 110 km Contract ended 20 Jul 2024, 681 days before the data date Past contract end Maintenance and stabilisation of the Mundhiriya, Imam Wais and Failaq road, 90 km, two lanes Contract ended 26 Apr 2026, 36 days before the data date Past contract end Sindiya bridge, 336 m Contract ended 2 Aug 2024, 668 days before the data date Past contract end Various roads across Khalis and its subdistricts in Diyala Contract ended 13 Sept 2025, 261 days before the data date Past contract end Completion works for a group of roads in Saadiya, Jizani al-Imam and Mansuriya Contract ends 26 Jul 2026 On track Second carriageway of the Hit to Haditha road, section two, from km 25 to km 50 Contract ends 15 Jul 2026 On track Widening of the embankment from the Saqlawiya concrete bridge to expressway intersection 51, 14.6 km, with a 2 km service road for low cost housing and a 1.7 km road from the Japanese bridge to the Nazim bridge Contract ended 10 May 2026, 22 days before the data date Past contract end Rehabilitation of the Ramadi to Rahaliya road, starting at the Kahawi area Contract ended 25 Aug 2025, 280 days before the data date Past contract end Maintenance and rehabilitation of the road linking Nukhaib and Karbala Contract ended 24 Apr 2026, 38 days before the data date Past contract end Ring and link roads for Ali al-Wardi city 32.5 points below planned progress Behind plan Reconstruction of the Rustamiya bridge Contract ended 1 Dec 2025, 182 days before the data date Past contract end Grand Baghdad bridge Contract ended 1 Apr 2026, 61 days before the data date Past contract end Fadhiliya concrete bridge, Baghdad Contract ended 9 Feb 2026, 112 days before the data date Past contract end Design and construction of the Zafaraniya bridge on the Dora to Yusufiya expressway road, reaching Harith bin Kalda street, with an overpass on the Dora to Yusufiya road, Baghdad 19 points below planned progress Behind plan New bridge over the Tigris with rehabilitation of the old Sarafiya bridge, two overpasses at the Sarafiya bridge and Buratha mosque intersections, and widening of the road between Sarafiya bridge and the Shalchiya intersection (second traffic congestion package) Contract ended 28 Nov 2025, 185 days before the data date Past contract end Design and construction of the road linking the Mohammed al-Qasim expressway and the Kirkuk to Baghdad road through Basatin and Suraidat, Baghdad Contract ended 22 Dec 2024, 526 days before the data date Past contract end Design and construction of an overpass at the Refinery intersection, linking the Double Decker bridge to the Suspension bridge, and a tunnel at Ahmed Orabi square, Baghdad Contract ended 20 Sept 2025, 254 days before the data date Past contract end Design and construction of the Abu Nuwas road widening and the new Jadriya overpass linked to the Nusoor square approaches via Umm al-Khanazir island, Baghdad Contract ended 22 Feb 2025, 464 days before the data date Past contract end Design and construction of the Kraiyat bridge, Baghdad 34.8 points below planned progress Behind plan Dora overpass on 60th street Contract ended 10 Oct 2025, 234 days before the data date Past contract end Design and construction of the Hurriya intersection, Karrada Kharij, including the Hasanain tunnel 82 points below planned progress Behind plan Development of the Ministry of Transport tunnel No progress data Shomali to Qasim road linked to the Qasim to Kifl road, 16.48 km Contract ended 25 Mar 2026, 68 days before the data date Past contract end Widening of the Kifl to Najaf road, 10.325 km Contract ended 14 Jan 2026, 138 days before the data date Past contract end Second carriageway linking Haswa city to the expressway Contract ends 3 Aug 2027 On track Maintenance of the Thermostone road, old lane, 10.5 km Contract ended 26 May 2025, 371 days before the data date Past contract end Rehabilitation of the Baghdad to Karbala road from the Dalla roundabout to checkpoint 54, Karbala Contract ends 21 Aug 2027 On track Maintenance and resurfacing of the Karbala, Razzaza and Ukhaidir road, phase one Contract ended 29 Apr 2026, 33 days before the data date Past contract end Partial ring road for Karbala Contract ends 14 Mar 2029 On track Second carriageway linking the Kifl to Qasim expressway, 30 km, Najaf (infrastructure) Contract ends 29 Aug 2028 On track Overland Hajj road (239 km), phase two, 50 km from km 77 to km 127, Najaf 11.5 points below planned progress Behind plan Widening of the Haidariya to Najaf and Karbala road, 15.64 km Contract ends 13 Jul 2026 On track Overland Hajj road (239 km), phase one, 50 km from km 27 to km 77, Najaf Contract ended 7 Jul 2025, 329 days before the data date Past contract end Third Kufa bridge (Imam Ali bridge) Contract ends 5 Sept 2026 On track Second carriageway of the overland Hajj road, phase three, 27 km Contract ended 4 Sept 2025, 270 days before the data date Past contract end Maintenance and rehabilitation of the quarries road, old lane, 27 km, Najaf Contract ended 1 Nov 2025, 212 days before the data date Past contract end Fifth Kufa bridge Contract ends 22 Jun 2028 On track Second carriageway of the Kut, Badra and Mehran road including the Kalal Badra bridge (76 km), phase two of 36.4 km with a bridge over Wadi Kalal and an overpass at the Badra city entrance, Wasit Contract ended 10 Jul 2025, 326 days before the data date Past contract end Second Numaniya bridge 14.2 points below planned progress Behind plan Widening and rehabilitation of the Kut to Baghdad main road within Wasit, 60 km (phase one) Contract ended 19 Oct 2024, 590 days before the data date Past contract end Maintenance of the old Kut, Badra and Mehran road, Wasit Contract ends 4 Jun 2026 On track Second carriageway of the Suwaira to Jabla road, Expressway No. 1 Contract ends 30 Sept 2028 On track Second carriageway of the Dabbouni to Jassan road and maintenance of the old road Contract ends 7 Jan 2029 On track Rehabilitation and widening of the Kut to Baghdad main road, 71.5 km Contract ends 3 Mar 2029 On track Diwaniyah to Hilla main road, phase one, 25.3 km Contract ends 10 Jun 2026 On track Maintenance of the Salam to Islah road, 15 km Contract ended 5 Sept 2025, 269 days before the data date Past contract end Dur al-Naft concrete bridge and approaches Contract ended 22 Apr 2026, 40 days before the data date Past contract end Abdullah bin Ali concrete bridge and approaches Contract ended 22 Apr 2026, 40 days before the data date Past contract end Qal'at Salih concrete bridge and approaches Contract ended 22 Apr 2026, 40 days before the data date Past contract end Rehabilitation and maintenance of the Amarah, Mashrah, Ghuzaila and Sheeb border road, 64.5 km Contract ended 15 Mar 2026, 78 days before the data date Past contract end Rehabilitation and maintenance of the Amarah, Butaira and Fajr road, outbound lane, 80 km Contract ended 4 May 2026, 28 days before the data date Past contract end Al Khalil (Al Ammar) bridge, Shatra district Contract ended 29 Jun 2025, 337 days before the data date Past contract end Remaining works on the north Nasiriyah bridge and approaches (phase one, river bridge), Dhi Qar (at the expense of the defaulting contractor) Contract ended 3 May 2026, 29 days before the data date Past contract end Rehabilitation and development of the single Dutch bridge Contract ended 10 May 2026, 22 days before the data date Past contract end Link from Nasiriyah to Expressway No. 1, 24.6 km 66.6 points below planned progress Behind plan Al-Rehab to Ain Saida and Al-Busaya road, 50 km, Muthanna Contract ended 24 Jul 2023, 1,043 days before the data date Past contract end Second carriageway of the Samawah to Mamlaha road (Abdullah Abu Najm road), 19.6 km with three bridges, Muthanna Contract ended 23 Jun 2023, 1,074 days before the data date Past contract end Maintenance of the Samawah to Nasiriyah road, old lane, 14 km Contract ended 6 Sept 2025, 268 days before the data date Past contract end Rehabilitation of the Jumaima border crossing Contract ended 21 Aug 2025, 284 days before the data date Past contract end Removal of the temporary steel bridge and construction of the Al-Ali concrete bridge Contract ended 22 Mar 2026, 71 days before the data date Past contract end Martyr Izz al-Din Salim bridge, 312 m, Basra 30.5 points below planned progress Behind plan Second carriageway of the Butaira, Fajr and Al Budair road, 52.35 km Contract ended 1 Nov 2025, 212 days before the data date Past contract end Settlement of accounts for completed and cancelled projects No progress data Rehabilitation of the Baghdad to Abu Ghraib expressway Contract ended 7 Dec 2025, 176 days before the data date Past contract end Expressway section T/6, right lane, km 0 to km 47 Contract ended 20 May 2025, 377 days before the data date Past contract end Bridges of expressway section T/6, km 0 to km 144.8 Contract ended 31 Aug 2023, 1,005 days before the data date Past contract end Link from the government complex to Expressway No. 1 at km 100 Contract ended 17 Dec 2025, 166 days before the data date Past contract end Link from Fallujah University to Expressway No. 1 Contract ended 19 Mar 2026, 74 days before the data date Past contract end Opening the route of the fourth ring road 77.4 points below planned progress Behind plan Expressway No. 1 rehabilitation, section T/4, phase one, 105 km Contract ended 27 Mar 2023, 1,162 days before the data date Past contract end Link from Karbala to the expressway 11 points below planned progress Behind plan Link from the Hamza road to Expressway No. 1 23 points below planned progress Behind plan Second carriageway at Tarmiya, Baghdad to Mosul entrance, 13 km, Baghdad Contract ended 12 Jun 2024, 719 days before the data date Past contract end Rehabilitation and maintenance of Expressway No. 1, section T/4, phase two Contract ends 22 Feb 2029 On track Completion works for the middle and final parts of the second carriageway of the Kisik to Rabia road, Nineveh Completed Development of the Badriya to Baadhra road, Nineveh Completed Completion works for the sixth Mosul bridge and approaches Completed Rehabilitation of the Baqaq bridge (second carriageway) Completed Rehabilitation and replacement of the second Quri Chay bridge on the old lane and approaches Completed Construction and rehabilitation of roads in Saadiya, Mansuriya and Jizani al-Imam linked to the Baghdad to Kirkuk road, 33.61 km Completed Second carriageway of the Jalawla to Qara Tapa road, 36.1 km Completed Rehabilitation and maintenance of the Baghdad to Kirkuk road, 64 km Completed Second carriageway of the Ramadi to Haditha road, 33 km, phase three, including Wadi Hajlan Completed Haditha bridge and approaches, 548 m, Anbar Completed Maintenance of the Ramadi to Hit road, 17 km Completed Rehabilitation of the Wadi Ghadaf bridge on the 160 km Nukhaib road, at km 54 Completed Fourth Fallujah bridge Completed Rehabilitation and maintenance of the Ramadi to Qaim main road from the Muhammadi roundabout to the Bastamiya checkpoint, 32 km westwards Completed Completion works for the Haditha bridge approaches Completed Maintenance, resurfacing and shoulder stabilisation of the Ramadi to Qaim main road from km 30.1 to km 47.1 (counting from the Haditha junction) Completed Rehabilitation of the road over the drain (Albu Haddad and Albu Shubail) Completed Rehabilitation of the road linking the villages of Albu Dhalil, Albu Dhib and Albu Dimna, 1,000 m long and 20 m wide Completed Maintenance of the Adhamiya bridge Completed Maintenance and rehabilitation of the Muthanna bridge Completed Bab al-Muadham bridge Completed Shuhada bridge Completed Aimma bridge Completed Maintenance of the steel (Awadil) bridge over the Diyala river Completed Design and construction of the new Baghdad Court intersection (formerly the General Security intersection) Completed Kardhiya bridge in Kut, phase two Completed Remaining works on the Kardhiya bridge in Kut, phase one Completed Second carriageway of the Ghammas junction to Hamza al-Sharqi road, 19 km Completed Maintenance and rehabilitation of the Diwaniyah to Najaf road, return lane, 19 km Completed Maintenance of the Sunniya to Albu Nail road, 10 km, Sunniya district Completed Replacement of the Mohammed Sadiq al-Sadr bridge Completed Rehabilitation and maintenance of the State Farm road, 12.91 km Completed Rehabilitation of the Diwaniyah, Al Budair and Fajr road (return side), 38 km Completed Maintenance of the Madhiya road in Ghammas district, 10.5 km Completed Rehabilitation of the road linking Sumer to Imam Ibn al-Abbas Completed Sababat concrete bridge Completed Maimuna bridge Completed Second carriageway of the Butaira to Amarah road, 5.148 km Completed Rehabilitation and maintenance of the Kut to Nasiriyah road, 28 km Completed Rehabilitation and maintenance of 8.3 km of scattered sections of the Fajr to Al Budair road Completed Maintenance of the Samawah, Mamlaha and Mamlaha intersection road, 23 km, and rehabilitation of three single lane bridges on the main road Completed Khidr concrete bridge (phase two) Completed Maintenance and furnishing of the Nasiriyah to Samawah road, 24 km, both directions Completed Maintenance of the Hilla to Kish road, 14 km (return lane) Completed Fixed pedestrian bridge in the Kraiyat area, Baghdad Completed Samawah branch road works (left lane), km 1.4 to km 27.144, Muthanna Completed Maintenance of the Bathaa bridge at km 142.7 Completed Rehabilitation of the heavy vehicle and tanker lane at the Suqur checkpoint Completed
No projects match this search.
Source: Ministry of Construction, status as of 1 Jun 2026Details
How status is worked out
Status is calculated from the official numbers only. Past contract end means the contract end date was before 1 Jun 2026 and progress is below 100%. Behind plan means actual progress is more than 10 points below planned. What is being built is our own grouping, read from the official project names. A project can be in more than one group, and offices and other buildings are in none. More about the data